Asbestos can be after found in walls, pipe isolating layers, fire-protection walls, chimney, cable, pipes, titles, wire and valve cover layers etc.

Safe and Healthy Working Environment for the Workers
Control region is set up. Control region is separated from other working areas that reduce the number of people to contact with the asbestos. Authorized people to enter to control region should wear the mask. All people to enter to region should wear the mask. Eating, drinking and smoking in control region is prohibited.

 Disposal Method of Asbestos
To reduce direct with asbestos, the methods and process control are introduced. Even to contact with asbestos, people can suffer less with certain density that is up to the stanard. With providing mask and breathing aids, people can suffer less. Partial ventilation and small particles collection system should built. All equipments such as saw, sand grind and drill, which may product asbestos dust, should be installed with partial ventilation system. No asbestos product such as cement, mortar, caoting or gypsum should be taken out from containers or bags unless it is carried out in spectial closed area. Compressed air should not be used to removed the asbestos unless equipped with special ventilation system.

Protection aids
Breathing Protection:
Masks should be provided to workers. Workers should wear the masks in the following conditions:
- Installation or execution of process and under operation control\
-  During repai or maintenance
-  When the contact of asbestos cannot be avoided
-  Emergency situation

 Procedure of taking breath protective aid
If the working environment beyond the safe limit, breath protective procedure are required. In order to ensure sufficient protection for our staffs in such working area, we provide the best airlight, electrical mask with filter for them. If it was proved that the mask was unsuitable or unsafe for the workers, or it was found that the worker was unfit for the duty, then we would appoint the other work for him.

Protective clothing and equipment for our workers
Type of protective clothing:
-  Overalls / boiler suits and etc
-  Gloves, safety helmet and safety shoes
-   Mask, safety goggle and other safety equipment assigning changing area
-  Change of dirty worker clothing ( with asbestos dust ) should only be done within such area. Unless authorized cleaning staffs / maintenances staffs / etc, nobody can be allowed to take away such dirty clothing out from the changing room.
-  All undressed dirty clothing should be put inside the assigned containers.
-  Labeling, markings of such containers for further disposal.

Laundry and renewal:
-  Cleaning, drying, maintenance or renewal of the protective clothing and equipment to keep them in good working order,
-  No blowing or fickering of the dirty clothing is allowed
-  Dirty clothing should be stowed into the enclosed containers and bags with label indicated for funture disposal.

 Hygiene Facilities:
Changing room and locker services are provided. Workers should take shower if they have workers in which density of asbestos exceeds the requires standards. All clothes or equipment should not be brought away from the working area.

 Management and Disposal of Asbestos
Treated asbestos should be packed with enclosed containers, doubles skin package and labeled with warning mark. Health, safety and environmental protection are our priorities. According to MSDS, treatment and dangerous goods should all comply with country and regional laws.

 Emergency Plan
Density of asbestos should be monitored anytime. Worker should be educated to concern health, safety and environmental protection. Alarm system should function well. Rescue teams are established including three safety teams in charge chaired by principal and minister. Medical services should be enhanced.

 

1.gif (634 字节) ASBESTOS
2.gif (634 字节) OIL
3.gif (633 字节) 有限空间
4.gif (634 字节) 切    割
5.gif (634 字节)

致冷剂

6.gif (634 字节) 个人防护用品
6.gif (634 字节) 预处理程序
     


Asbestos Train


Asbestos Region


Asbestos Disposal


Asbestos Storage

sailing.gif (2381 字节)  Back       Chinese Version   Vessels Photos  Broken In Yard!     

Meeting with PONL

 


             CHANGJIANG  SHIP-BREAKING  YARD
              JIANGYIN CITY JIANGSU PROVINCE CHINA
                 PHONE:86-510-86168805( J.F.QIU)      FAX:86-510-886166107

                 E-MAIL:cjshipbr@pub.wx.jsinfo.net